Feasibility review
Building Code · Updated Nov 16, 2026

Zoning says what. The Code says how.

Short answer

Zoning decides what you can build and where it sits. The Ontario Building Code decides how it’s built safely: structure, fire separations, exits, sound, plumbing and access. The 2024 Code has been in force since January 1, 2025, and every permit application since April 1, 2025 must use it.

  1. What is the 2024 Ontario Building Code?
  2. Which version applies to my project?
  3. The Code questions that drive multiplex cost
  4. Fire access for rear-yard suites
  5. Who takes responsibility for the design?

What is the 2024 Ontario Building Code?

It is O. Reg. 163/24 under the Building Code Act, 1992. It adopts the 2020 National Building Code of Canada with Ontario amendments, and it replaced the 2012 Code (O. Reg. 332/12). Ontario says it eliminated at least 1,730 technical variations from the national code.

Which version applies to my project?

  • Permit issued on or before December 31, 2024: the 2012 Code, if construction started within six months.
  • Drawings substantially complete by December 31, 2024 and application made by March 31, 2025: the 2012 Code was still allowed.
  • Applications from April 1, 2025: the 2024 Code.

The Code questions that drive multiplex cost

  • Fire separations and sound control between units.
  • Exits and egress, especially from basement units.
  • Smoke alarms and carbon monoxide detectors, shown on every floor plan.
  • Stairs, guards and handrails, detailed in sections.
  • Plumbing: no plumbing serving one unit may run in or under another unit unless it’s accessible in a tunnel, pipe corridor, common basement or garage, though piping from an upper unit may run through the unit below.
  • Clearance from overhead electrical conductors, confirmed by a designer declaration on new buildings and additions.

Fire access for rear-yard suites

The Code requires fire department access to every building by a street, private roadway or yard (Div. B 9.10.20.3.). Toronto’s pre-approved suite plans translate that into a 45-metre prescriptive limit from the street, or up to 90 metres with added protection such as sprinklers, an exterior strobe and alarms. For garden suites these requirements can’t be varied at the Committee of Adjustment.

Who takes responsibility for the design?

Toronto’s Schedule 1 designer information form is required for designers other than architects and engineers, and owners who are exempt from designer qualification must state why. Even with a pre-approved plan, the owner or designer who uses it is responsible for the design.

FAQ

Questions, answered.

Is the Ontario Building Code the same as zoning?

No. Zoning (a municipal by-law) controls use and building envelope. The Building Code (a provincial regulation) controls construction and safety. A permit needs both.

When did the 2024 Building Code take effect?

January 1, 2025, with a transition period for certain designs until March 31, 2025.

Can a minor variance waive a Building Code rule?

No. Minor variances relate to zoning. Fire access for garden suites is a Code matter that can’t be varied at the Committee of Adjustment.

Do I need smoke and CO alarms shown on my drawings?

Toronto’s conversion guide asks for floor plans showing smoke alarms and carbon monoxide detectors.

The offer

The Lot Feasibility Review.

Send an address. Get back the truth about your lot.

What zoning allows: units, height, depth, suites
A build-cost range and a rent range for your lot
Financing paths and rebates you may qualify for
A straight recommendation — including “don’t build”

[Price / guarantee: TBD]