The permit path, step by step.
In Toronto, a multiplex that fits zoning needs a building permit, not a rezoning. Check your zone and envelope, design within it, and get a Zoning Applicable Law Certificate if you want certainty. If the design needs relief, get a minor variance first. Then apply through Toronto Building Online Services and build with inspections.
Step 1: Is the use permitted?
Find your zone on the Interactive Zoning By-law Map. Duplexes, triplexes and fourplexes are permitted in the R, RD, RS, RM and RT zones. Five or six units are permitted in detached buildings on Neighbourhoods lots in Wards 4, 9–14, 19 and 23. Elsewhere, six-unit permissions vary by location.
Step 2: Does the building fit?
Permission to have the units is not permission for any size of building. Height (in metres, with a 10-metre floor for multiplexes), lot coverage, setbacks and any Chapter 900 exception set the envelope. FSI limits in the zone label don’t apply to multiplexes.
Step 3: Get a Zoning Applicable Law Certificate (recommended)
A Zoning Applicable Law Certificate is a detailed preliminary review that confirms zoning and other applicable law compliance, so the permit application is complete. It includes up to three reviews. Fees for 2026 run from $644.38 (house of up to two units, conversions, garden and laneway suites) to $888.14 (other buildings up to 300 m²) and $1,863.82 (over 300 m²). The fee is credited to your building permit when you use the certificate.
Step 4: Minor variance, if you need one
If the design breaks a zoning standard, apply to the Committee of Adjustment before the building permit. The Committee applies four Planning Act tests: is it minor, is it desirable for the appropriate development of the land, does it maintain the intent of the Zoning By-law, and does it maintain the intent of the Official Plan. All four must be met, for every variance.
Step 5: Apply for the building permit
Apply through Toronto Building Online Services. For a conversion, the City lists a site plan referenced to a current survey, fully dimensioned floor plans (including smoke alarms, CO detectors and plumbing fixtures), sections, and construction details and notes. Exterior work also needs a municipal road damage deposit, and a Tree Declaration Form is required where trees could be affected. Intake checks completeness. Missing items come back to you, then an examiner reviews.
Step 6: Build, inspect, occupy
Once the permit is issued, construction proceeds with City inspections at the stages listed on your permit. Related mechanical, plumbing and drain permits can be submitted once the building permit application is in. Keep every permit, plan and inspection record. Lenders, insurers and the Landlord and Tenant Board may ask for them later.
Where projects lose time
- Incomplete applications, which wait for resubmission.
- Designs that need variances discovered late.
- Tree conflicts found after design.
- Fire access problems for rear-yard suites, which can’t be varied.
- Changes to pre-approved suite plans, which void the pre-approval.
Sources
- City of Toronto — Considerations When Building Multiplexes
- Toronto Zoning By-law 654-2025 (five- and six-unit multiplexes)
- City of Toronto — Multiplex Housing
- City of Toronto — Zoning Applicable Law Certificate
- City of Toronto — Committee of Adjustment Participation Handbook
- City of Toronto — Garden Suites
- City of Toronto — Multiplex Conversion permit guide
- City of Toronto — Pre-approved garden & laneway suite plans
- Ontario — Residential rent increases
- Ontario — The 2024 Ontario Building Code
Accessed Nov 16, 2026. General information, not legal, tax or financing advice.